Steel piping and connection joints

Steel piping and drive shoe

To avoid infiltration of sand and/or contaminated surface water, we install a minimum of 20' of superior quality steel piping. We thus respect the Ministry of the Environment's regulations.

This piping must absolutely be anchored in the rock formation with a drive shoe, so as to ensure the integrity of your well and avoid infiltrations of surface water.

Connection joints

When the rock formation is located at more than 20' from the surface of the soil, we must install additional steel piping. It is essential to join the lengths of piping with a ring and weld the upper and lower parts of the ring, in order to avoid infiltration of surface contaminants.